Next stage of our major marina maintenance

Thursday, 9th May 2019

Dear Members

I’m pleased to advise the next stage of our major marina maintenance works gets underway from 15 May 2019. The works include the replacement of timber walers, cleats and thru-rods in the following areas;

  • The main walkway on row D East
  • The main walkway including the T Head on Row D West
  • The 7 finger pontoons on row C East and including berths 149/150
  • Other ongoing concurrent works include additional pedestal upgrades and pile bracket replacements.

The works may take up to 8-10 weeks. Please note that whilst works are undertaken in the above areas, services including water and power may at some point be switched off.  We will be in touch with boat owners as updates come to hand.

So if you are on the marina during these works, please take extra care and communicate with the contractors as appropriate. Whilst we understand there will be a very short inconvenience, we are continuing to make a sizeable investment in improving the Marina and we again ask for your patience and understanding during this time.

Immediately on the back of these works, we intend on commencing works addressing F Row and the balance of the main walkway between E & F Rows – we will be in touch again re: the timing of this work.

See you around the Club.